Wednesday, 24 August 2016

Changes ahead at the airport ...

A radical restructuring of regional airports will proceed ...

Fraport Greece, the German company will manage by the end of the year 14 regional airports for about 40 years.

Recently the European Fund for Strategic Investment (EFSI) the EIB approved 300 million in funding. For the provision of 14 regional airports in the Fraport (the total financing for the whole project may reach 400 million.)

The company aims to cover, to the season of 2017, the largest shortfalls in direct infrastructure.

Just take the regional company: they repaired the sanitation, baggage and delivery procedures will be simplified, electronic bulletin boards and renewed signs will be repaired.

In a second phase planned construction work, such as the extension of the terminals of airports, new restaurants and shops.

According to the concession agreement, the Greek-German consortium Fraport Slentel has a comprehensive program of construction works to upgrade 14 regional airports,
It is estimated that by the end of the 40-year concession will increase the number of passenger movements at around 52 million.



Skiathos the current width of the runway is 75 meters from the central axis and therefore does not comply with the requirements of the ICAO standards.

Yet there is not enough space at the end of runway 20 to provide a sufficient safety zone End Corridors (RESAs), as the area limited by road routes and sea.

Will move the baggage system, will expand the baggage hall and office spaces in the existing plant will be relocated. Following these works planned expansion of 2,953 sq.m. terminal, providing sufficient capacity until the end of the concession period.

Source: http://www.thenewspaper.gr/


Note: A number of hits requesting info on August 23rd 1944 - See the link on yesterdays blog entry